Offtaker: EETC Egypt
Lenders: IFC, EBRD, ICBC,AIIB, ADB, CDC, Finnfund, OE & EAB
Location: Aswan - Benban Site
Capacity Size: 1650 MWp
System: Feed in Tariff (FiT Round 2)
Mounting Type: Single Access Tracker
Duration: 7 Month
Developer : Alcazar
EPC : TSK/Enviromena
Scope: Civil, Electrical, Mechanical works
No. of Plots: 4
Projects: AEES, HORUS, DELTA, ATEN
Scope Capacity Size: 256 MWp
Solar installer have started the biggest training program in Egypt, based in Aswan, covering 290 Engineers, supervisors, and technicians (Civil – Electric – Mechanical – communication) , most of them were hired in the project.
Trenching Scope: 57,504 m2
Cable Laying Scope:-
Cables Laying: 1,659,000 m2
Steel Wire: 267,000 M
Conduit: 81,000 M
Trenching Scope: 57,504 m2
Cable Laying Scope:-
Cables Laying: 1,659,000 m2
Steel Wire: 267,000 M
Conduit: 81,000 M
Inverter Scope (off loading / Installation & Termination): 54
Skid Scope: 27
Concrete Scope: 1326 m2
String box Installation & Termination: 1188
Control Box Installation & Termination: 6468
Post Ramming Scope: 5000
Developer: Alcazar , TAQA Arabia
EPC Main Contractor: TSK/Enviromena Sterlin & Wilson
Scope: Procure & Construct
Projects: AEES, HORUS, DELTA,ATEN
Fence Size: 18 KM
Duration: 2 Month